|
FEDERAL ENERGY
REGULATORY COMMISSION, WASHINGTON, D.C. 20426 - NEWS RELEASE
NEWS MEDIA CONTACT: FOR IMMEDIATE RELEASE
Bryan Lee November 16, 2006
(202) 502-8680 Docket No. RM06-12-000
COMMISSION FINALIZES ELECTRIC TRANSMISSION SITING RULE
The Federal Energy Regulatory Commission today approved a final rule
governing the filing requirements and procedures for entities asking
the Commission to exercise its supplemental authority to site
interstate transmission facilities under the Energy Policy Act of
2005.
Commission Chairman Joseph T. Kelliher observed: "One of the major
goals of the landmark Energy Policy Act of 2005 was strengthening
our Nation's power grid. Today, the Commission takes final action to
implement the transmission siting provisions of the Act. Our
approach was very respectful of state authority. As a practical
reality, I would expect states will continue to site the vast bulk
of transmission projects. Congress did not provide for exclusive
federal siting authority, and we will use our authority to
supplement state transmission siting."
The biggest change from the proposed rule relates to the initiation
of prefiling at the Commission. Under the proposed rule, an
applicant was barred from making a formal application for a federal
construction permit until one year after initiation of a state
proceeding. But prefiling could be initiated earlier, and could
overlap with the state siting proceeding. In response to state
concerns, the final rule bars both a formal application and the
initiation of prefiling within one year of initiation of a state
proceeding.
The Energy Policy Act provides for supplemental federal
authorization of certain electric transmission facilities in
national interest electric transmission corridors designated by the
Secretary of Energy. In these corridors with power grid capacity
constraints or congestion that adversely affects consumers, the
Commission may issue permits to construct or modify electric
transmission facilities if the Commission finds:
(1)a state in which a facility is located does not have siting
authority, or state law does not consider interstate benefits;
(2)the applicant for the facility is a transmitting utility but does
not qualify to apply for siting approval in the state because the
applicant does not serve end-use customers in the state;
(3)a state with siting authority either withholds approval for more
than one year after the application is filed, or one year after the
designation of the relevant corridor, whichever is later; or
(4)the state conditions its approval such that it will not
significantly reduce transmission congestion or it is not
economically feasible.
The Commission's final rule addresses comments received from 51
entities in response to a June 16, 2006, notice of proposed
rulemaking. The final rule largely affirms the approach outlined in
the proposed rule.
A proposal to build or expand electric transmission facilities: must
apply to facilities that will be used for transmission in interstate
commerce; be consistent with the public interest and enhance energy
independence; significantly reduce transmission congestion in
interstate commerce and protect or benefit consumers; be consistent
with national energy policy and enhance energy infrastructure; and
maximize, to the extent reasonable and practicable, existing towers
or structures.
The rule encourages maximum participation from all interested
stakeholders through a Public Participation Plan and an extensive
pre-application and post-application process. The participation plan
provides all interested parties, including affected landowners, with
information on all aspects of the proposed project, including
national and local benefits and environmental impacts. The
participation plan provides for public involvement during the
pre-filing and application processes, and must be accessible in a
central location in each county through which the proposed project
would be located.
The pre-filing process includes consultation with the Director of
the Office of Energy Projects (OEP) to determine a project's
eligibility for pre-filing, the start of environmental review under
the National Environmental Policy Act, numerous public participation
opportunities, and a determination by the Director of OEP that an
application is ready to be filed for Commission consideration.
Once an application is filed, the rule requires public notification
of the application, issuance and solicitation of comments on the
draft environmental document, preparation and issuance of a final
environmental document, a review of the record and issuance of a
final decision by the Commission.
The following are among the significant decisions the Commission
made in the final rule:
- The Commission's pre-filing process will not commence until one
year after an application has been filed for state review.
- The Commission declined to establish specific criteria on how it
will determine whether states have authority to approve the siting
of transmission facilities or consider interstate benefits, deciding
instead to make these determinations on a case-by-case basis.
- Entities seeking to invoke Commission jurisdiction on the basis of
a state's failure to act timely will be required to pursue the
requisite application with the state one year prior to commencing
pre-filing at the Commission.
- The Commission will consider all information filed with the states
as part of its review of the proposed project. However, the
Commission is required under the National Environmental Policy Act
to conduct its own, independent review of potential environmental
impacts.
- The Commission clarified how it intends to implement its
notification requirements, with respect to entities that must be
notified regarding the project, and how an interested person may
access information and participate in the Commission's proceedings.
- The Commission eliminated from the final rule a proposed property
value impact analysis, concluding that concerns regarding the
accuracy of such studies could delay the development of transmission
projects.
- The Commission will convene a number of regional technical
outreach conferences after issuance of the final rule.
The final rule, "Regulations for Filing Applications for Permits to
Site Interstate Electric Transmission Facilities," takes effect 60
days after publication in the Federal Register.
For further information, go to
http://www.ferc.gov/industries/electric/indus-act/siting.asp
R-06-72
(30)
|